NFPA 25 Sprinkler Inspection Schedule

The NFPA 25 inspection, testing, and maintenance schedule for wet and dry sprinkler systems — with which tasks trained staff can perform in-house.

  1. 1Address
  2. 2Facility
  3. 3Systems
  4. 4Details
  5. 5Dates
  6. 6Review
Facility address

Printed on every output — the calendar header and log sheets. You can skip it and add it later.

Free · No signup. Your dates and facility details stay on your device — every calculation happens on your device.

NFPA 25 schedule

Every requirement carries its code section and the edition it was verified against. ★ = qualified in-house under the national code, but licensing commonly required locally — confirm with your AHJ.

This is not one schedule from one edition. The rows below were verified against different editions of NFPA 25 (2020 and 2023), shown per row in the Code column. Section numbers and intervals move between editions, and we have not determined which edition your jurisdiction has adopted — read each row against the edition beside it and confirm with your AHJ rather than treating the table as a single document.

TaskFrequencyWho may performCode (edition)Record
Gauges + control valves (dry / pre-action / deluge)WeeklyIn-house (basic)NFPA 25 Table 5.1.1.2 (2023)Log
Gauges + alarm valves (wet systems)MonthlyIn-house (basic)NFPA 25 Table 5.1.1.2 (2023)Log
Control valves: sealed / locked / supervised, correct positionMonthlyIn-house (basic)NFPA 25 §13.3 (2023)Log
Waterflow alarm devices, supervisory devices, FDC conditionQuarterlyIn-house (qualified)NFPA 25 §5.3.3 / §13.7 (2023)Test record
Main drain test at each riser (backflow / PRV on sole supply)QuarterlyIn-house (qualified)NFPA 25 §5.3.3 (main drain quarterly where sole supply passes through backflow preventer or PRV) (2023)Static + residual pressures; compare to prior; >10% drop investigated
Main drain test (all risers)AnnualIn-house (qualified)NFPA 25 §13.2.5 (2023)Pressures vs prior year
Full inspection — heads, pipe, hangers, bracing, signage, spare headsAnnualCertified / licensedNFPA 25 §5.2 (2023)Report + deficiency list
Internal pipe assessment (obstruction investigation)Every 5 yearsCertified / licensedNFPA 25 §14.2 (2023)Report
Sprinkler head sample test — standard-response heads (50 years, then every 10)Every 50 yearsCertified / licensedNFPA 25 §5.3.1 (2023)Lab report
Sprinkler head sample test — fast-response heads (20 years, then every 10)Every 20 yearsIn-house (qualified)NFPA 25 §5.3.1.1.1.2 (2020)Laboratory test report.
Dry-pipe / pre-action full trip test with control valve wide openEvery 3 yearsIn-house (qualified)NFPA 25 §13.4.4.2.2 (3-year full trip) (2020)Trip test report with trip time and water delivery time.
Dry-pipe valve partial trip test (priming water, low-point drains)AnnualIn-house (qualified)NFPA 25 §13.4.4.2.1 (annual partial trip) (2020)Valve test report.
Antifreeze solution test — specific gravity / freeze point at each loopAnnualIn-house (qualified)NFPA 25 §5.3.4 (antifreeze) (2020)Solution test record per loop.

Other schedules: NFPA 72 · NFPA 96 · NFPA 110 · NFPA 80 · NFPA 10

National consensus-standard baseline with the edition noted per item. Your state, fire marshal, or accrediting body may require more frequent service or licensed personnel where a qualified person is shown. General information, not legal or engineering advice — confirm with your AHJ.

Questions people ask

How often does NFPA 25 require inspection?
NFPA 25 sets a schedule from weekly, monthly, quarterly, annual intervals. The full task-by-task table with code sections and who may perform each task is shown above, and the calendar builder dates it from your real last-completed dates.
Which of these tasks can be done in-house?
Tasks marked Tier 1 or Tier 2 can be performed by trained facility staff with documentation under the national code. Tier 3 tasks require a certified or licensed professional. Starred tasks are qualified in-house under the national code but licensing is commonly required locally — confirm with your AHJ.