Indiana fire drill log

Fire exit drills quarterly on EACH SHIFT, at least twelve a year, held under varied conditions so personnel meet the signals and the required action in different circumstances. Each drill must include the transmission of a fire alarm signal AND simulation of emergency fire conditions — a walk-through without the alarm does not count.

The building

Indiana requirements loaded — the rules below are Indiana’s own.

IndianaResidential Care Facility: Fire exit drills quarterly on EACH SHIFT, at least twelve a year, held under varied conditions so personnel meet the signals and the required action in different circumstances. Each drill must include the transmission of a fire alarm signal AND simulation of emergency fire conditions — a walk-through without the alarm does not count.410 IAC 16.2-5 (residential care facilities); comprehensive care facilities at 410 IAC 16.2-3.1 · Indiana Department of Health · checked Jul 2026
Your target for the year

36 drills this year. 12 per shift × 3 shifts = 36 a year.

We assumed three shifts, since this licence is staffed around the clock. Change it below if that is wrong.

Worked out from Indiana Department of Health's rule as we have it recorded. Confirm it against your licence before you rely on it — then leave the box below empty and we will keep using this number.

0 of 36 logged, 36 to go.
The drills

One row per drill. Vary the time of day and the scenario — most states require it explicitly, and a log showing four drills all at 10am on a Tuesday is the first thing a surveyor notices.

1

What Indiana requires

Residential Care FacilityGroup home / residential care home

Fire exit drills quarterly on EACH SHIFT, at least twelve a year, held under varied conditions so personnel meet the signals and the required action in different circumstances. Each drill must include the transmission of a fire alarm signal AND simulation of emergency fire conditions — a walk-through without the alarm does not count.

410 IAC 16.2-5 (residential care facilities); comprehensive care facilities at 410 IAC 16.2-3.1 · Indiana Department of Health · 410 IAC 16.2-5 · checked July 2026

Filling it in so it survives a survey

Vary the time and the scenario between drills — most states require it in terms, and a log showing every drill at 10am on a Tuesday is the first thing an experienced surveyor picks out. Record what went wrong and the date it was fixed: a run of flawless drills reads as a log nobody actually ran, and the corrective action is the part that shows the drill was worth holding.

The plan behind the drills

A drill tests a plan. Everything Indiana requires of that plan — filing, prescribed forms, retention — sits alongside this, and the emergency plan builder writes it from the same research, so the two cannot disagree.

Everything else we’ve researched about Indiana

Same state, the problems either side of this one. Each carries its own statute and the date we last checked it.